If the optimistic estimate for an activity is 12 days, and the pessimistic is 18 days, what is the PERT standard deviation of this activity?
a) 1
b) 1.5
c) 3
d) 6

Respuesta :

Otras preguntas

Need Help, thanks:) Please help
If you waited until late in life to start saving, what two things should you try to do?
What would you enter at the command prompt to display the shared library information for executables?
Find the slope of each line
what is the significant personal cost associated with the flu
In △BCD, BP=15 cm. What the length of BX¯¯¯¯¯¯ ? __cm
joey can spend no more than 28 dollars on Mp3 downloads. if each song cost 1.29 and it cost 9.99 to buy the entire album. Joey wants to the new like Bryan albu
Drag each description to the correct location on the image. Not all descriptions will be used. Describe the parts of a comet. The descriptions are: The frozen p
Read this passage from Dragonwings by Laurence Yep. During those trips alone among the demons, Father and I learned things about one another; and more, we learn
What are the advantages of using context clues as your primary tool/strategy for discovering the definitions of unknown words? What are the disadvantages?