The flowtime of the last job in a single work center’s schedule is 7 days. What is the makespan of this schedule?

Respuesta :

Tundexi
Tundexi Tundexi
  • 14-01-2021

Answer:

7 days

Explanation:

Makes-pan means the time it takes to complete a schedule. Last job took 7 days to complete and it was a single job, which means its makes-pan was 7 days as well.

Answer Link

Otras preguntas

A cell with 12 chromosomes undergoes mitosis. How many daughter cells are created? each daughter cell has chromosomes.
which of the following characteristics did Simón Bolívar and José de San Martín share? They came from the working class and represented the people They were par
1. What drew Americans to settle in the northeast region of Mexico?​
Evaluate the expression when m=4 and n=31. n-3m
What is the sign of -xy?
write 5 idioms on happy, sad and unforgettable moment .​
Someone please help me!
Consider this as a simultaneous-move (static) game: Player B Left
32 1/3% of animals at an animal shelter are dogs. About what fraction of the animals are dogs
Which statement is the best counterclaim for this claim? The government should allocate more funds to space exploration and research. A. The government should f