is A and B can do a piece of work in 6 and 12day respectively how m
any part of work can they do in 4 day​

Respuesta :

wolf1728
wolf1728 wolf1728
  • 12-08-2021

Answer:

6 * 12 / (6+12) = 72 / 18

If they work together they can finish in 4 days.

Source: http://www.1728.org/work.htm

Step-by-step explanation:

Answer Link

Otras preguntas

How do authors present and develop characters? Check all that apply.
6) What is the purpose of the final four stanzas? A) It symbolically mirrors the knight's inner conflict. B) The refrain echoes stanza 1, thus providing much ne
Write each expanded expression as a power. 1.7 x 1.7 x 1.7 =
Tra Figure P was rotated about the center shown by 180°. P Tra center Which figure is the image of P? Qu Choose 1 answer: 809 Tak A А P Р Ro B B P Р Qu 0% Tal P
Flo and Carl each must read a 500-page book. Flo reads one page every minute. Carl reads one page every 50 seconds. Flo starts reading at 1:00, and Carl starts
(+8) + (-2) I need to understand this
What does Bud’s mom mean when she compares him to a flower bud?
DONT GET THIS 20 POINTS!!!! What is the value of x?
An item is regularly priced at $77. Yasmin bought it at a discount of 15% off the regular price.
Does anybody have a teachers pay teachers account where they can buy a pdf?