A piece of work takes 20 labourers to complete in 10 days. how many labourers will complete the same job in 25 days if they work at the same rate?​

Respuesta :

denimjackets23
denimjackets23 denimjackets23
  • 04-09-2021

Step-by-step explanation:

If 20 labourers=10 days

x labourers = 25 days

10x= 25×20

[tex] \frac{10x}{10} = \frac{25 \times 20}{10}[/tex]

Cancelling out by 10 on both sides

[tex]x = \frac{25 \times 2}{1} \\ x = 50 [/tex]

Therefore, it takes 50 labourers to complete the work at the same rate in 25 days.

Answer Link

Otras preguntas

spade realty sold lots for $23240 per hectare . what is total sales values if the lots in hectare were 2,3,4 ?
9,835/63 what is the answer and what is the remainder
i hate this brainly thing so so so much
Omar has $660 to spend at a bicycle store for some new gear and biking outfits. Assume all prices listed include tax. He buys a new bicycle for $330.64. He buys
True or false everyone in the colonies could vote
DONT delete my question or else!!! AM i a awful person??
Gavin was thinking of a number. Gavin subtracts 10 from it and gets an answer of 2.7. What was the original number?
What is the term for the type of venation seen on a ginkgo tree? Help meeeee
HELP ASAP ELA POEM!!!!! I will give brainlist the the first person!!! Write your own poem imitating Mary Oliver poem called "the wild geese" by following this f
1+0.9+0.08+0.001 Somebody can help me please