3 workers can do a job in 28 hours. How many more workers are needed to do this job in 12 hours?

Respuesta :

Laita
Laita Laita
  • 13-03-2022

Answer:

7 workers

Step-by-step explanation:

[tex]\frac{workers first time}{workers second time} = \frac{hours second time}{hours first time}[/tex]

[tex]\frac{3}{x} = \frac{12}{28}[/tex]

cross multiply and it becomes

12x = 3x28

12x = 84

x = 84/12

x = 7 workers

Answer Link
mjl2011ljm
mjl2011ljm mjl2011ljm
  • 17-03-2022

Answer

4

Step-by-step explanation:

3/28=x/12

that is 7 and you need to find how many more workers so you subtract

7-3=4

Answer Link

Otras preguntas

The graph of the function f(x) = –(x + 3)(x – 1) is shown below. On a coordinate plane, a parabola opens down. It goes through (negative 3, 0), has a vertex at
Dr. Patel properly washes her hands before every surgery. Hand washing is an example of a safeguard. A first-aid step. An injury. An accident.
Why do you think it is so important that financial records are maintained well? What would be a potential negative consequence be to not maintaining financial r
Need help on doing escape room. How to escape from Emoji Planet.
somebody answer i need Help​
Find the measure of 2 116 90 26 64
Where did the funding to build the large towns on the eastern coast of Africa come from?
Arrange this in ascending order :10; -200; -75; 150 ; 0; 150; 75; -210​
Refer to these stories from the Iliad: "Prologue: The Long Siege," "The Quarrel," and "Hector and Andromache." What is a theme in "Prologue: The Long Siege," "T
How does this vase make you feel? Why? Hellppp helppp