In a project network, the critical path is the sequence of activities which has the:________.

Respuesta :

66hello60
66hello60 66hello60
  • 03-08-2022

Answer:

The correct answer is the longest time

Answer Link

Otras preguntas

A heartbeat take 0.8 second how many seconds is this written as a fraction
Why were Europeans so interested in exploration in the 1400s and 1500s? A) They wanted to spread Christianity. B) They believed it was their destiny to spread a
1) express 23kg in miligrams
4. Identify the predominant climate of South America. (1 point) temperate arid polar tropical 5. Which of the following bird species is found almost exclus
The amount of labor the heart must exert to pump blood throughout the body is known as the _____.
Initially, the MOST successful European colonial power was
How to put this in order from least to greatest 0.5, 3/16, 0.75, 5/48
If you graph both sides of an identity, what will the graph look like
most fish enjoy a lunch or dinner of worms. which identifies the direct object(s) in the sentence? A.enjoy B.fish C.worms D.lunch, dinner
Which result is a positive aspect of globalization? intense competition decreased profit margins increased coordination costs business expansion