If it takes 4 workers 21 hours to paint how many hours will it take 12 workers?

Respuesta :

m11233982
m11233982 m11233982
  • 12-09-2022

Answer:

63 hours

Step-by-step explanation:

4 workers = 21 hours

12 workers = g

[tex] \frac{21}{4} \times 12 \\ = 63hours[/tex]

Answer Link

Otras preguntas

Yesterday the number of cars sold was 6. the average number of cars sold is typically 10 per day with a standard deviation of 3 cars per day. what is the z-scor
What is the mean of 85,89,95,71,80,85,76
Which of these is the BEST example of debt? A) A person buys a new car. B) A person pays interest on a mortgage. C) A person deposits a paycheck into a saving
During the process of mountain building A. material from the Earth's interior is often returned to the surface. B. the Earth's interior often gains mat
the formula y=2.4sqrt (x)+15 models the percent of U.S. adults that are obese by federal guidelines, were
Last word) the inverse dependency ratio is predicted to fall to about 1.16 by 2050. what is the most likely effect of this decline? multiple choice it will like
list three properties if the elements that are useful in sorting the elements.
Does anyone at all know this please help
a war in Mexico would be under the what command
Mike and tom debone chicken breasts for ted's chicken co. mike is new and can only debone 30 chicken breasts per hour by hand, while tom's experience allows him