Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

ASAP WILL GIVE BRAINLY!!!!!!!!!!!!!!!!! A dance team is made up of 9 girls and 3 boys. Two of the girls and 1 of the boys are also on the debate team. What perc
write a perfect sentence and paragraph asp​
DNA nucleotides are always added to an existing strand at the 3-prime end. This means that during replication, a leading strand and a lagging strand are created
A chemical reaction can theoretically produce 137. 5 grams of product, but in actuality 112. 9 grams are produced. Which is the percent yield for this reaction?
Mark graphed points on the coordinate plane below to represent the locations of his school and a bank. Mark wants to add the location of the library on the coor
How many miles is a light year
Despite the original purpose of the Philadelphia convention, which was to revise the Articles of Confederation, from its beginning prominent delegates were dete
i dont want to read a book
2 cups of flour makes of a loaf of bread. How much flour is needed for 1 whole loaf?
I will give you Brainliest! Which sentence uses active voice?