Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Why are cells so important for organisms?
Which expression is a factor of x2 +2x - 15 A. (x - 3) B. (x + 3) C. (x + 15) D. (x - 5)
how did manufacturing change the way americans fought the civil war
Suppose that Mystic Energy and E-Storm are the only two producers of hydrogen fuel cells. The market inverse demand curve for hydrogen fuel cells is P = 1,300 –
There are ten kids in a class. When any two meet, they shake their hands.Before the class starts, how many handshakes are there?
Explain the rationale of using hexadecimal notation by computer programmers
ANSWER ASAP!! remember to show work​
who created humans on earth
HELP PLEASE ASAP!!!!Adult Golden Retrievers have a mean weight of 64 pounds with a standard deviation of 8 pounds. If you take a random sample of 35 gold retrie
Franklin the frog is competing in a frog jumping contest, Franklin takes three jumps and six steps and lands at 24 Write an equation to represent the situation,